Sorry Flo - but it ain't me making all these decisions. I am but a piper who is playing but a more and more melancholic tune. But.....to return to this Southdown Avenue development. Seems it is for 20 houses with 30% originally being for Affordable Housing. Seems it is viability issues that is causing this no AH request. The viability issues are, of course, confidential.
Reference: 16/00844/MOD Address: Land At Southdowns Road, Dawlish, Devon, Proposal: Application for modification of Section 106 agreement relating to Planning Permission 13/00943/MAJ to remove affordable housing pr...
So what happens if parcel 3 does not get developed? What might need to happen in order for that to be achieved? What would be the consequences if it wasn't developed? This is covered from 2.4.2 through to 2.4.11 of the report.
Because the report is concerned with the costings and delivery etc of the link road only?
Okay, so.......the route of the link road goes over parcel 4 (NHS Langdon land), parcel 3 (Secmaton Farm land) and parcel 2 (Gatehouse Farm land). As the report points out, both parcels 2 and 4 can be developed independently of parcel 3. But......remember the link road has to cross parcel 3 in order for it to connect Sainsbury's roundabout with Secmaton Lane/top end of Elm Grove Road. ...
TDC have now placed this online - Dawlish Link road options report https://www.teignbridge.gov.uk/CHttpHandler.ashx?id=46830&p=0 "It is understood that the findings of this work will be considered by members at the same meeting as the initial planning applications and the Draft SPD". ie at the TDC planning meeting on Tuesday 5th April 2016.
No
and now there is this DawlishDeservesBetter
Yesterday someone told me about this cycle. Have a read of this for instance http://www.progressiveproperty.co.uk/blog/18-year-property-cycle/ which was written a couple of years ago. So.......if we are approximately in the middle of the latest housing boom/bust cycle then if that link road doesn't get built NOW whilst the market is bouyant, then come a few years time when the ...
This morning I lodged with TDC planning department 2 x objections on the grounds of traffic access/lack of link road to planning application 15/02700/Maj (200 dwellings, care home and employment land at Langdon) and 15/02468/Maj (409 dwellings, extra care unit at Gatehouse). I explained about the safety and environmental issues arising from the DCC Highways proposal that right turning ...